A buyer in Nairobi opens a container of 40 × 40 × 2.0 mm galvanized square tube and puts a caliper on the first length. The reading is 1.79 mm. He checks nine more: 1.81, 1.77, 1.82, 1.80, 1.78, 1.83, 1.79, 1.76, 1.81. Every one of them is inside the standard. None of them is inside the number he thought he had bought. Nothing has been forged, and the supplier has not lied — the order simply went out without a tolerance class, so the mill shipped to the bottom of the range it is allowed to use.
This is the most common commercial dispute in the hollow section trade, and it repeats every quarter because the fix sits in eight words of a purchase order rather than in the mill.
Cold-formed hollow sections are governed by tolerances that most buyers never read. EN 10219-2 allows roughly ±10 percent on wall thickness. ASTM A500 allows ±10 percent as well. GB/T 6728, the Chinese standard behind most export tonnage, follows a similar band. On a nominal 2.0 mm wall, the legal floor is around 1.8 mm. On a 3.0 mm wall it is 2.7 mm.
The arithmetic is unforgiving because mass per metre is driven by section perimeter times thickness. For a square tube:
kg/m = (A + B − 2t) × t × 0.0157, with A and B as outside dimensions in millimetres and t as wall thickness.
A 40 × 40 × 2.0 mm length works out to (40 + 40 − 4) × 2.0 × 0.0157 = 2.386 kg/m. At the tolerance floor of 1.8 mm, the same profile gives (80 − 3.6) × 1.8 × 0.0157 = 2.159 kg/m. That is 9.5 percent less steel in every length, on a product sold by weight. On a 25-tonne order the buyer pays for 25 tonnes and takes delivery of the weight, but the container carries roughly 2.4 tonnes less steel than the nominal specification promised. Structures built to that steel are also about 9 percent weaker in bending than the drawing assumed, which is the part that does not appear on the invoice.
Hot strip is bought by weight, zinc is bought by weight, and tube is sold by weight, so the incentive runs in one direction. A line running consistently at minus 8 percent improves yield by roughly that amount with no visible change to the product. Serious mills control the middle of the range because they know the second order depends on it; traders chasing a price per tonne do not, and the difference only appears when the container is opened.
The practical defence is a wall thickness clause with a positive bias: "wall thickness 2.0 mm, tolerance +0.1/−0.05 mm, spot-checked at four points per length, 10 lengths per bundle." It costs a few dollars per tonne and removes the argument entirely.
Both are sold as "galvanized square tube", and they behave differently in service. Pre-galvanized tube is formed from zinc-coated strip, typically Z100 to Z275, so the flat faces carry a uniform coating of 7 to 19 µm per side. The weld zone and every cut end are bare steel. Post-galvanized tube is fabricated first and dipped in molten zinc afterwards, which seals the ends and the weld, and produces a coating in the 45–85 µm range — ISO 1461 asks for a 45 µm minimum on steel 1.5–3 mm thick and 55 µm on 3–6 mm.
On a fence frame in a dry climate, pre-galvanized is the economical answer. On a coastal solar mounting structure, a greenhouse frame in a humid belt, or anything that will be cut and drilled on site, the unprotected cut ends of pre-galvanized tube become the first corrosion sites, and the coating cannot protect what it does not cover. This is why S220GD hot-dip zinc-coated structural tube is specified for exposed frames while lighter site work often uses pre-galvanized material.
Strength class matters alongside the coating. S280GD galvanized structural pipe carries a 280 MPa minimum yield, which is what a racking or mezzanine design usually assumes; substituting a 235 MPa commercial grade quietly removes around 15 percent of the capacity. If the drawings specify a structural grade, the mill certificate has to name it.
White rust is not a coating failure, but it is treated as one at the receiving dock. Wet bundles, tight strapping and a six-week sea voyage in a container with no ventilation produce zinc hydroxide on surfaces that never dry. The coating is still there, but the customer sees white patches and rejects the delivery.
Prevention is procedural: passivation after galvanizing, drying before strapping, ventilation gaps between layers, desiccant in the container, and avoiding loading during rain. A supplier who packs on the day of galvanizing and loads the same afternoon will deliver white rust in a humid season. Ask what the packing sequence is, not whether the tube is galvanized.
Square tube is bought for its outside dimensions, and the dimensions that fail on site are usually the ones nobody specified: corner radius, straightness, twist and length. Standard cold-formed sections carry an outside corner radius of roughly twice the wall thickness — about 4 mm on a 2 mm wall — and a fabricator expecting a sharp corner will find his miter joints open. Straightness of 1 mm per metre is normal; 3 mm per metre is not, and it shows up as a bowed rail across a six-metre span.
Length tolerance deserves a line too. Six metres with +10/0 mm is standard. Buyers cutting to 5.8 m for container loading need to say so, because a bundle of 6.0 m lengths will not fit a 40-foot high cube without diagonal stowage, and the freight penalty lands on the buyer.
Most of these are one-line additions. Together they turn a commodity order into a specification, and they explain why two quotes for "40 × 40 × 2.0 galvanized" can differ by 60 dollars a tonne without either supplier being dishonest. The galvanized square and rectangular tube range covers sizes from light fencing sections to heavy structural profiles, and square and rectangular hollow sections remain the most heavily shipped line, which is precisely why the tolerances are worth writing down. For round sections used in the same frames, the galvanized steel pipe programme follows the same rules.
The buyer in Nairobi did not lose money because the mill cheated him. He lost it because a purchase order said 2.0 mm and nothing else, and in the hollow section trade a number without a tolerance is an invitation.